How to Design a Three-Phase Home ESS for EV Charging and Heat Pumps: A Worked Example

The House Has a 22 kW EV Charger. The Battery Does Not Need to Be 22 kW.

A three-phase Home ESS should be sized from the loads that actually overlap, not by adding every appliance nameplate rating. For a home with an EV charger and heat pump, the design should establish the grid-import limit, phase configuration, controllable EV charging power, heat-pump demand, battery/inverter power, usable battery energy, solar contribution, and backup scope. EV charging is usually the most flexible large load; heating and essential loads usually receive higher priority.

How to Design a Three-Phase Home ESS for EV Charging and Heat Pumps - A Worked Example

This worked example uses illustrative numbers rather than representing a specific Ruibit/Dawnice customer project.

The objective is to see how the design decisions interact.

The House

Assume a European-style three-phase home with:

Grid supply: 3 × 25 A
Rooftop PV: 12 kWp
EV charger: 11 kW, three-phase
Heat pump: 3.5 kW typical electrical input
Other household loads: 1.5 kW typical evening load
Proposed battery: 20 kWh class
Home ESS inverter: three-phase

The theoretical three-phase grid capacity at 400 V is approximately:

√3 × 400 × 25 ≈ 17.3 kW

That number immediately matters.

If the EV charger consumes 11 kW while the heat pump and household simultaneously require another 5 kW, the house is already close to the connection limit before another major appliance starts.

The battery can help.

But load control may be cheaper than designing the battery to solve every possible coincidence.

18:10 — The Car Plugs In

The homeowner arrives home.

At that moment:

EV charger requests: 11.0 kW

Heat pump: 3.5 kW

Household loads: 1.5 kW

Total:

16.0 kW

The battery does not need to supply 16 kW.

The grid is still available.

Suppose the energy-management strategy limits grid import to:

12 kW

Required battery contribution becomes:

16 − 12 = 4 kW

A suitable Home ESS could discharge approximately 4 kW to hold the grid near the selected limit.

But there is another option.

Reduce EV charging from 11 kW to 7 kW.

Now:

7 + 3.5 + 1.5 = 12 kW

Battery discharge required:

0 kW

This is why I would integrate EV load management before simply buying a larger battery inverter.

The EV may remain connected for eight hours.

It usually does not need maximum charging power every minute.

19:30 — Cooking Changes the Equation

Now add:

Induction cooking: 3 kW

If the EV is still charging at 7 kW:

EV: 7.0 kW
Heat pump: 3.5 kW
Cooking: 3.0 kW
Other loads: 1.5 kW

Total:

15 kW

The EMS has choices.

It could discharge the battery by 3 kW.

Or reduce EV charging by another 3 kW.

Or combine both.

For this house, I would probably give load priority roughly as:

Essential household loads

→ Heat pump

→ Cooking

→ EV charging

The EV becomes the adjustable load.

That prevents the Home ESS from wasting expensive battery cycles simply because the car could not wait twenty minutes at full charging power.

How to Design a Three-Phase Home ESS for EV Charging and Heat Pumps - A Worked Example

Now Size the Battery Inverter

The battery still needs meaningful power capability.

Suppose the design objectives are:

limit normal grid import

increase solar self-consumption

shift evening energy

provide selected backup

After modelling the load profile, assume we determine that 8–10 kW of three-phase battery-inverter power handles the useful battery duties without trying to independently supply every connected appliance.

That does not mean any 10 kW inverter is suitable.

I would verify:

three-phase output architecture

per-phase limitations

battery voltage window

battery charge/discharge current

PV input limits

grid requirements

backup/EPS behavior

BMS communication

and how the EMS coordinates the EV charger.

For a Ruibit/Dawnice Home ESS quotation, the battery, inverter, meter/CT and controllable loads should therefore be treated as one operating system.

How Much Battery Energy?

Now move from kW to kWh.

Assume the battery's main daily job is to cover evening household and heating demand after solar production falls.

From 17:00 to 23:00, suppose the home consumes:

Heat pump: 9 kWh

Other household loads: 6 kWh

EV energy supplied from battery: 2 kWh

Total battery-supported demand:

17 kWh

A 20 kWh-class battery now looks reasonable.

But I would not assume all 20 kWh reaches the AC loads.

Usable SoC range, inverter losses, battery limits and backup reserve reduce the energy available for everyday dispatch.

If the homeowner reserves 20% for outages, the EMS should not spend that same energy on EV charging just because the evening tariff is expensive.

Midday Solar Changes Tomorrow's EV Energy

The next day, the 12 kWp PV array produces strong midday surplus.

Instead of exporting everything, the battery charges.

If the EV is parked at home, another option appears:

PV → EV directly

This can be more efficient than:

PV → battery → EV later

when the vehicle's schedule allows it.

So the control hierarchy should consider:

House loads first

Heat-pump demand

Battery charging / reserve target

Flexible EV charging

Grid export

The exact priority depends on tariffs and homeowner objectives.

There is no universal sequence.

What Happens During a Grid Outage?

This is where I would deliberately change the rules.

The homeowner may want:

refrigeration

lighting

internet

heat pump

selected sockets

but not:

11 kW EV charging

electric oven

other discretionary high-power loads

That means the backup load might be only:

4–6 kW

rather than the 15–20 kW the house can occasionally demand during normal operation.

This distinction can dramatically reduce the inverter and battery capacity required for useful resilience.

If EV charging during outages is genuinely required, it should be specified explicitly and the system sized accordingly.

Do not let "whole-home backup" accidentally become "every load operates normally forever."

The Final Design Is a Control Strategy

Our preliminary system might therefore look like:

Design Element Worked Example
Grid Three-phase, ~17.3 kW theoretical connection capacity
PV 12 kWp
EV charger 11 kW, dynamically controlled
Heat pump ~3.5 kW typical input
Home ESS inverter 8–10 kW class, three-phase
Battery ~20 kWh class
Grid-import target 12 kW example
Backup Selected essential loads + heat pump
EV during outage Disabled
Control priority Essential loads / heating before EV

These are worked assumptions, not a universal product recommendation.

A different household may need 15 kWh.

Another may need 30 kWh.

A larger heat pump, 22 kW charger, three EVs, electric resistance heating, different grid connection, or different tariff can change the design completely.

The important lesson is the sizing sequence:

Grid constraint → load coincidence → flexible loads → inverter kW → battery kWh → backup boundary → control strategy

not:

11 kW EV charger + 8 kW heat pump = buy a 19 kW battery inverter.

In a three-phase home, the best battery design often comes from deciding which loads do not need to run at full power at the same time .

That is especially true for EV charging.

Use the Home ESS for energy that needs to move through time. Use load management for power that can simply wait.

How to Design a Three-Phase Home ESS for EV Charging and Heat Pumps - A Worked Example

FAQs

1. Does an 11kW EV charger require an 11kW home battery inverter?

Not necessarily. EV charging is usually a flexible load. Dynamic load management can reduce charging power when the heat pump, cooking equipment, or other household loads are operating, reducing the battery power required.

2. How should a three-phase Home ESS be sized for an EV charger and heat pump?

Start with the grid connection limit and simultaneous household loads , then identify which loads can be controlled. Size inverter kW for the useful peak battery contribution and battery kWh for the required energy shifting and backup duration.

3. Should an EV charger operate from the home battery during a grid outage?

Usually it is more practical to prioritize essential household loads and heating while disabling or limiting EV charging. If EV charging during outages is required, the battery and inverter must be specifically sized for that additional load.

4. Why is dynamic EV charging useful with a Home ESS?

Dynamic charging can reduce EV power when household demand rises and increase it when capacity becomes available. This can prevent grid-limit violations and avoid unnecessary battery discharge or inverter oversizing.